Question 14

A and can completea task in 12 days. However, A had to leave a few days before the
task was completed and hence it took 16 daysin all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?


Create a FREE account and get:

  • Download RRB Study Material PDF
  • 45+ RRB previous papers with solutions PDF
  • 300+ Online RRB Tests for Free

cracku

Boost your Prep!

Download App