The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?
We know that efficiency ∝$$\frac{1}{no. Of working days}$$
Given that efficiency of work P and Q are in the ratio of 5 : 7
∴ Ratio of number of days taken by them to finish the work = 7 : 5