In the following questions, a question is followed by data in the form of two statements labelled as I and II. You must decide whether the data given in the statements are sufficient to answer the questions.
How many days are needed for A to complete a piece of work?
I) A and B require 20 days to complete the work
II) A takes 20 days more than B to complete the work