Crack XAT 2025 In 1-month. Enroll in crash course by Sayali ma'am (XAT 99.998%iler)
Edit MetaData
X can finish a work in 30 days, Y can finish a work in 12 days and Z can finish a work in 15 days. Y and Z start the work, but are forced to leave after 3 days. The remaining work was done by X in how many days?
9 days
16 $$\frac{1}{2}$$ days
8 $$\frac{1}{2}$$ days
18 $$\frac{1}{2}$$ days
Create a FREE account and get:
Login to your Cracku account.
Enter Valid Email
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!
Quick, Easy and Effective Revision
By proceeding you agree to create your account
Free CAT Formulae PDF will be sent to your email address soon !!!
Join cracku.in for Expert Guidance.