Question 37

A contractor undertakes to dig a canal 12 km long in 350 days and employs 45 men. He finds after 200 days of working that only 4 1/2 km of canal have been completed. How many extra men must be employed to finish the work in time?

Create a FREE account and get:

  • Download Maths Shortcuts PDF
  • Get 300+ previous papers with solutions PDF
  • 500+ Online Tests for Free