Question 54

If Manish can complete 3/5 of a work in 48 days, then Manish will complete 1/5 of the same work in how many days?

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free