Question 96

The steps involved in project approval are as follows:
A. Carrying out a detailed project analysis
B. Developing infrastructure prototype for project development
C. Generating a business idea
D. Performing a project specific factor analysis
E. Conducting a free-feasibility analysis

Choose the most appropriate answer from the options given below that shows right sequence

Solution

The correct order of sequence is:

C. Generating a business idea

D. Performing a project-specific factor analysis

E. Conducting a pre-feasibility analysis

A. Carrying out a detailed project analysis

B. Developing an infrastructure prototype for project development

In this sequence, the project approval process starts with generating a business idea. Then, a project-specific factor analysis is performed to assess the various factors and considerations specific to the project. Next, a pre-feasibility analysis is conducted to evaluate the feasibility and viability of the project. After that, a detailed project analysis is carried out, taking into account all relevant aspects of the project. Finally, an infrastructure prototype is developed for project development.

Therefore, the correct sequence is CDEAB.


Create a FREE account and get:

  • All Quant Formulas and shortcuts PDF
  • 40+ previous papers with detau solutions PDF
  • Top 500 MBA exam Solved Questions for Free

cracku

Boost your Prep!

Download App