The steps involved in project approval are as follows:
A. Carrying out a detailed project analysis
B. Developing infrastructure prototype for project development
C. Generating a business idea
D. Performing a project specific factor analysis
E. Conducting a free-feasibility analysis
Choose the most appropriate answer from the options given below that shows right sequence
The correct order of sequence is:
C. Generating a business idea
D. Performing a project-specific factor analysis
E. Conducting a pre-feasibility analysis
A. Carrying out a detailed project analysis
B. Developing an infrastructure prototype for project development
In this sequence, the project approval process starts with generating a business idea. Then, a project-specific factor analysis is performed to assess the various factors and considerations specific to the project. Next, a pre-feasibility analysis is conducted to evaluate the feasibility and viability of the project. After that, a detailed project analysis is carried out, taking into account all relevant aspects of the project. Finally, an infrastructure prototype is developed for project development.
Therefore, the correct sequence is CDEAB.